Change reference periods

You can change the reference periods for work times in your factory calendar.

Prerequisite

You have the Factory calendar management function privilege.

Procedure. Procedure
  1. Click PPM > Administration.

  2. Administration opens on a separate tab.

  3. Click Factory calendar in the Administration bar.

  4. Display the Base tab bar.

  5. Click Edit Edit.

    You can now edit the factory calendar.

  6. Select the Default settings tab.

  7. Select a reference period. To shorten a reference period, you need to select the preceding or following reference period and extend it.

  8. Click Edit Change reference period.

  9. Enter the first and last day of the reference period. Reference periods may begin on any day of the week, but must include at least one week.

  10. To select the date using a calendar, click Calendar Set date and enter the date.

  11. Click OK.

  12. Click Yes.The preceding or following reference period will be reduced automatically.

  13. Click Save Save.

Your settings are saved in the PPM database.

Tip

You can enter changes to working times covering less than one week as special times.