Skip to main content

Get help for ARIS Process Performance Manager

Color measure values based on planned values in tables

If you have specified planned values for a measure, you can color the measure values in your list tables or crosstabs based on the planned values.

Prerequisite

You display your analysis as a list table or crosstab.

Procedure. Procedure
  1. Display the Query tab bar.

  2. Click Reference Show comparison values.

  3. Enable the Planned values option for the relevant measures.

  4. Click OK.

  5. Display the Visualization tab bar.

  6. Click n_ppm_analyse_planwerte_einblenden Planned values > Highlight in color.

Depending on your settings, the measure values are colored as follows:

  • green: better than planned value 1

  • yellow: between planned value 1 and planned value 2

  • red: worse than planned value 2